How four Southeast Asian grids carried electricity to Singapore

The first phase imported Lao hydropower through Thailand and Malaysia using existing links. Phase two raised the maximum to 200 MW and added Malaysia as a possible source of supply, alongside its original transit role.

Sources checked

MilestonesAgreements and capacity in the cross-border project
  1. September 2021
    Exclusive framework agreement

    Keppel Electric and Électricité du Laos announced the framework Source 1

  2. 23 June 2022
    Imports begin

    Lao hydropower through Thailand and Malaysia to Singapore Source 1

  3. Phase one
    Initial capacity

    Up to 100 MW through existing interconnections Source 1

  4. 20 September 2024
    Phase two announced

    Maximum 200 MW, with additional supply from Malaysia Source 2

  5. 20 September 2024
    Singapore licence extended

    EMA granted Keppel a further two years to 2026 Source 2

The project connects national grids and commercial agreements, with phase two expanding the sources of supply.

Source 1 Source 2 Source 3

The commercial sale used three physical interconnections

In 2022 Keppel Electric began importing power from Électricité du Laos. The route passed from Laos through Thailand, then Malaysia, then into Singapore. The first phase used links that were already in place, so the project combined access to existing grids with a new multilateral arrangement. Source 1 Source 3

Malaysia acquired a second role

Under the original route, Malaysia’s grid was part of the transit chain. EMA’s September 2024 announcement says the next phase adds electricity supplied by Malaysia. That additional source underpins the increase from a maximum of 100 MW to 200 MW. The 200 MW describes the enhanced project as a whole. Source 2 Source 3

The importer licence and power agreement cover different parties

The first agreement described in the launch release was between Keppel Electric and Électricité du Laos. Singapore’s EMA separately regulates the ability to import electricity. Its 2024 announcement extended Keppel’s importer licence to 2026 in support of the second phase. The contract, licence and grid access each address a distinct part of the trade. Source 1 Source 2

Capacity and delivered energy are different measures

An import limit is expressed in MW. A flow of 100 MW held for one hour would deliver 100 MWh, but the limit alone gives no evidence about how many hours the power actually flowed. EMA lists separate electricity import trials elsewhere on its regional grids page, so their figures should be tracked separately from this four-country project. Source 2 Source 3