Source data
Milestones and roles in the four-country power project
Sources checked
- September 2021Exclusive framework agreement
Keppel Electric and Électricité du Laos announced the framework Source 1
- 23 June 2022Imports begin
Lao hydropower through Thailand and Malaysia to Singapore Source 1
- Phase oneInitial capacity
Up to 100 MW through existing interconnections Source 1
- 20 September 2024Phase two announced
Maximum 200 MW, with additional supply from Malaysia Source 2
- 20 September 2024Singapore licence extended
EMA granted Keppel a further two years to 2026 Source 2
The project connects national grids and commercial agreements, with phase two expanding the sources of supply.
Milestones and roles in the four-country power project
The MW figures are limits on power at a point in time. Delivered energy over a period is measured separately in MWh.
| Source | |||
|---|---|---|---|
| September 2021 | Exclusive framework agreement | Keppel Electric and Électricité du Laos announced the framework | Source 1 |
| 23 June 2022 | Imports begin | Lao hydropower through Thailand and Malaysia to Singapore | Source 1 |
| Phase one | Initial capacity | Up to 100 MW through existing interconnections | Source 1 |
| 20 September 2024 | Phase two announced | Maximum 200 MW, with additional supply from Malaysia | Source 2 |
| 20 September 2024 | Singapore licence extended | EMA granted Keppel a further two years to 2026 | Source 2 |