Malaysia’s actual data centre load and December 2025 pipeline
Sources checked
The bars show dated actual load. Contracted demand and other project stages appear in the table.
Malaysia’s actual data centre load and December 2025 pipeline
Power is expressed in MW. The December connected, construction and agreement rows are separate stages within the pipeline total. Actual load is a separate operating measure.
| Source | ||||
|---|---|---|---|---|
| December 2024 | Actual load | 405 | Source 2 | |
| September 2025 | Actual load | 710 | Source 2 | |
| December 2025 | Actual load | 850 | Source 1 | |
| December 2025 | Final contracted demand for connected projects | 4,500 | 35 | Source 1 |
| December 2025 | Projects under construction | 1,800 | 14 | Source 1 |
| December 2025 | Projects at supply agreement approval stage | 1,200 | 7 | Source 1 |
| December 2025 | Total pipeline | 7,500 | 56 | Source 1 |